Page 12 - Chehalis Tribal Newsletter - March 2025
P. 12
Chehalis Behavioral Health Center
Chehalis Behavioral Health Center
WEEKLY PROJECT UPDATE
WEEKLY PROJECT UPDATE
October 18, 2024
October 18, 2024
CHEHALIS TRIBAL NEWSLETTER Chehalis Behavioral Health Center
The Confederated Tribes STAFF
of the Chehalis Reservation,
‘People of the Sands’ Communications Coordinator
Frazier Myer, Communications
Articles and opinions expressed Specialist Bobbie Bush,
are not necessarily those of this Designer Audra J. Hill and the
publication or the Chehalis Tribal Information Technology Team
Business Committee. Install Base Course for Parking Lot WEEKLY PROJECT UPDATE
TRIBAL CENTER
SUBMISSIONS Main line: 360-273-5911
Tribal members are encouraged Address: 420 Howanut Road BUSINESS COMMITTEE © copyright 2025
to submit birthday and anniversary Oakville, WA 98568
wishes, letters, articles, photos Office: 360-709-1726 Chairman: Dustin Klatush The Chehalis Tribal • Install Base Course for Parking Lot
and drawings to be considered Fax: 360-273-5914 Vice Chairwoman: Sheilah Bray Newsletter is a
for publication in the newsletter Treasurer: Farley Youckton publication of the
Secretary: Cheryle Starr
Confederated Tribes
(materials are subject to editing). VISION STATEMENT Chehalis Behavioral Health Center Chehalis Behavioral Health Center
Contributing writers, artists and To be a thriving, self-sufficient, Fifth Council Member: of the Chehalis
photographers include Chehalis sovereign people, honoring our Thomas Trott Reservation Framing in Roof Cricket
tribal community members/staff. past and serving current and future generations.
WEEKLY PROJECT UPDATE WEEKLY PROJECT UPDATE C A: Interior Wall Framing
12 October 18, 2024
October 18, 2024 October 18, 2024 C A: • Framing in Roof Cricket
• Interior Wall Framing
Chehalis Behavioral Health Center
Chehalis Behavioral Health Center
Weekly project update: March 14, 2025
WEEKLY PROJECT UPDATE
October 18, 2024
Current activities
n Install suspended ceiling
grid
C A: n Painting walls
Above: n Staining and ENS top coat
• Install Base Course for Parking Lot
John Lupo at CLT deck
C A: C A:
works on n HVAC trim at hard lids and
suspended ceiling
gutter
• Framing in Roof Cricket
installation. n Fire sprinkler trim at
Left:
• Interior Wall Framing
HVAC and suspended ceiling and
hard lids
electrical at
the grid. n Light fixture install at
• Exterior Wall Framing and Sheathing ceiling grid • • •
• Install Base Course for Parking Lot
n Prep for curbs and
Upcoming activities SPECIAL REMINDERS PEASE • Install Base Course for Parking Lot
sidewalks
• Pull Wire for Lighting at CLT Panels
n Grind and polish concrete AND EVENTS CONSTRUCTION n Install fall protection Chehalis Behavioral Health Center
Pease Construction working on interior framing and sheathing
TEAM MEMBERS
slab Safety requirements: Tano Bailon, system at roof
Boots, hard hats, safety
n Start exterior soffit glasses, high-visibility Steve Kathman, n Install gutters and trim
• Electrical R/I for EV Chargers and
staining and top coat work gear Jacob Phipps WEEKLY PROJECT UPDATE
Generator
n Exterior trespa siding n Finish WRB systems
U A:
• Framing in Roof Cricket
n Form and place SUBCONTRACTORS ON SITE • Framing in Roof Cricket
concrete curbs (weather Confederated, DL Henricksen, October 18, 2024
permitting) John Lupo, PEP Electrical,
n Install hollow metal door
• Install Roof Hatch Todd Robinson, TRS Mechanical
at exterior storage rooms
• Set Hollow Metal Frames
• Interior Wall Framing
• Install WRB’s and Flashings • Interior Wall Framing
• Electrical R/I at Exterior Walls
THE CBHC TEAM HAS WORKED 230 DAYS WITH ZERO ACCIDENTS!
• Plumbing R/I at Walls
• GWB Top Down
John Lupo working on drying in the roof and over framing at cricket
Exterior Wall Framing and Sheathing
• Exterior Wall Framing and Sheathing P C T M
•
Tano Bailon, Steve Kathman, Jacob Phipps, Ross Fields, Hans Wolfe Connor
Fields, Frank Deyette, Shawn Meehan, Rex Turner, Casey Baker
S O
Confederated Construction, PEP Electric, MC Pipemasters, TRS Mechanical John Lupo
• Pull Wire for Lig
• Pull Wire for Lighting at CLT Panels S R / E hting at CLT Panels
Pease Construction working on interior framing and sheathing
Pease Construction working on interior framing and sheathing
C A:
Safety Requirements- Boots, hard hats, safety glasses, high visibility
work gear
Excavation for site electrical
Excavation for site electrical
THE CBHC TEAM HAS WORKED 125 DAYS WITH ZERO ACCIDENTS! hargers and
• Electrical R/I for EV Chargers and • Electrical R/I for EV C
Install Base Course for Parking Lot
Generator
Generator • PEASE Construction, Inc.—General Contractors
P. O. Box 98046, Lakewood, WA 98496 P: (253) 584-6606 F: (253) 581-7855 www.peaseinc.com
Framing in Roof Cricket
U A: U A:
•
Interior Wall Framing
•
• Install Roof Hatch • Install Roof Hatch
• Set Hollow Metal Frames • Set Hollow Metal Frames
Exterior Wall Framing and Sheathing
•
• Install WRB’s and Flashings • Install WRB’s and Flashings
• Electrical R/I at Exterior Walls • Electrical R/I at Exterior Walls
Pull Wire for Lighting at CLT Panels
•
• Plumbing R/I at Walls • Plumbing R/I at Walls Pease Construction working on interior framing and sheathing
• GWB Top Down
• GWB Top Down Electrical R/I for EV Chargers and
C A:
• Generator John Lupo working on drying in the roof and over framing at cricket
John Lupo working on drying in the roof and over framing at cricket
P C T M P C T M
U A:
Tano Bailon, Steve Kathman, Jacob Phipps, Ross Fields, Hans Wolfe Connor
Tano Bailon, Steve Kathman, Jacob Phipps, Ross Fields, Hans Wolfe Connor
Fields, Frank Deyette, Shawn Meehan, Rex Turner, Casey Baker Fields, Frank Deyette, Shawn Meehan, Rex Turner, Casey Baker
S O S O
Confederated Construction, PEP Electric, MC Pipemasters, TRS Mechanical John Lupo
• Install Roof Hatch Confederated Construction, PEP Electric, MC Pipemasters, TRS Mechanical John Lupo
• Set Hollow Metal Frames
S R / E
S R / E
• Install WRB’s and Flashings
Electrical R/I at Exterior Walls
•
• Safety Requirements- Boots, hard hats, safety glasses, high visibility Safety Requirements- Boots, hard hats, safety glasses, high visibility
work gear
work gear
Plumbing R/I at Walls
•
Excavation for site electrical Excavation for site electrical
GWB Top Down
Excavation for site electrical Excavation for site electrical
THE CBHC TEAM HAS WORKED 125 DAYS WITH ZERO ACCIDENTS! John Lupo working on drying in the roof and over framing at cricket
• Install Bas
P. O. Box 98046, Lakewood, WA 98496 P: (253) 584-6606 F: (253) 581-7855 www.peaseinc.com e Course for Parking Lot Fields, Frank Deyette, Shawn Meehan, Rex Turner, Casey Baker
THE CBHC TEAM HAS WORKED 125 DAYS WITH ZERO ACCIDENTS!
P C T M
Tano Bailon, Steve Kathman, Jacob Phipps, Ross Fields, Hans Wolfe Connor
PEASE Construction, Inc.—General Contractors
PEASE Construction, Inc.—General Contractors
S O
P. O. Box 98046, Lakewood, WA 98496 P: (253) 584-6606 F: (253) 581-7855 www.peaseinc.com Confederated Construction, PEP Electric, MC Pipemasters, TRS Mechanical John Lupo
S R / E
Safety Requirements- Boots, hard hats, safety glasses, high visibility
work gear
Excavation for site electrical
Excavation for site electrical
• Framing in Roof Cricket
THE CBHC TEAM HAS WORKED 125 DAYS WITH ZERO ACCIDENTS!
PEASE Construction, Inc.—General Contractors
P. O. Box 98046, Lakewood, WA 98496 P: (253) 584-6606 F: (253) 581-7855 www.peaseinc.com
• Interior Wall Framing
• Exterior Wall Framing and Sheathing
• Pull Wire for Lighting at CLT Panels Pease Construction working on interior framing and sheathing
• Electrical R/I for EV Chargers and
Generator
U A:
• Install Roof Hatch
• Set Hollow Metal Frames
• Install WRB’s and Flashings
• Electrical R/I at Exterior Walls
• Plumbing R/I at Walls
• GWB Top Down
John Lupo working on drying in the roof and over framing at cricket
P C T M
Tano Bailon, Steve Kathman, Jacob Phipps, Ross Fields, Hans Wolfe Connor
Fields, Frank Deyette, Shawn Meehan, Rex Turner, Casey Baker
S O
Confederated Construction, PEP Electric, MC Pipemasters, TRS Mechanical John Lupo
S R / E
Safety Requirements- Boots, hard hats, safety glasses, high visibility
work gear
Excavation for site electrical
Excavation for site electrical
THE CBHC TEAM HAS WORKED 125 DAYS WITH ZERO ACCIDENTS!
PEASE Construction, Inc.—General Contractors